Lifting of conveyor / 2013

Pietarsaari 2013 Lifting of Conveyor

Lifting of conveyor in Pietarsaari 2013

Length of load 125m, weight of load approximately 100 tons. Five mobile cranes, 500t, 200t, 2x160t and a 100t, were needed for the lift in tandem. The conveyor was lifted in one single piece. In addition, some access platforms were used. It took around 48 hours to complete the lift.